Parliamentary Question · No. B/839 · Series B Answered

the Chemin Grenier Market Fair Project, he will state the reasons for the delay in the coming into operation…

Asked by
Mr Jugurnauth
Second Member · Savanne and Black River
Addressed to
Local Government
Minister of Local Government
Sitting
Tuesday, 7 October 2025
Question 26 of 89
The question, as placed

(No. B/839) Mr S. Jugurnauth (Second Member for Savanne & Black River) asked the Minister of Local Government whether, in regard to the Chemin Grenier Market Fair Project, he will state the reasons for the delay in the coming into operation thereof. Madam Speaker: Minister of Local Government, straight-forward answer, please!


The exchange, in full
Mr Woochit

Yes, Madam Speaker. Madam Speaker, the construction of the new Chemin Grenier Market Fair started on 11 October 2021 and was initially scheduled to be completed by 10 October 2022. Following the approval of the Central Procurement Board, the contract was awarded to RBRB Construction

45 Ltd on 31 August 2021 for an amount of Rs107.5 million, and this figure includes a contingency sum of Rs5 million, excluding of VAT after a discount of Rs12.5 million. The contractor took possession of the site on 27 September 2021. Madam Speaker, I am advised that the project faced several unforeseen challenges during implementation, which caused delays. I am tabling a comprehensive report outlining the detailed reasons for the delay in the completion of the Chemin Grenier Market Fair, which includes – • the adverse climate conditions, including frequent heavy rainfalls and floodings onsite; • non-performance of the former Project Manager, who was also the appointed architect for the project; • changes in the scope of the sub-structure due to the topography of the land; • unavailability of expatriate labour faced by the contractor, resulting from the restrictive policies of the outgoing government; • additional works allocated to the contractor for the construction drainage system, and • poor project management by the District Council of Savanne, among other contributing factors. Madam Speaker, I am informed by the District Council of Savanne that the project will be fully completed within the next two weeks. This will be followed by an expression of interest exercise for the allocation of stalls to vendors. It is expected that the Chemin Grenier Market Fair will become operational by mid-December 2025. Thank you.

Madam Speaker

Hon. Third Member for Vieux Grand Port and Rose Belle! UNION PARK, BEEMANIQUE & CLUNY REGIONS – HEAVY TRAILERS – ROAD USERS’ SAFETY & ENVIRONMENTAL THREATS