Republic of Mauritius · National Assembly2024–2026 · 26ᵉ THERE MAY BE ERRORS OR INCONSISTENCIES Wednesday, 20 May 2026

The Hansard Record

Parliamentary Questions, in full — public, searchable, copypastable.
Parliamentary Question · No. B/1199 · Series B Answered

the proposed construction of a Market Fair near the Youth Centre in Mahebourg, he will, for the benefit of t…

Asked by
Mr Apollon
Second Member · Mahebourg and Plaine Magnien
Addressed to
Local Government
Minister of Local Government
Sitting
Tuesday, 9 December 2025
Question 26 of 69
The question, as placed

(No. B/1199) Mr T. Apollon (Second Member for Mahebourg & Plaine Magnien) asked the Minister of Local Government whether, in regard to the proposed construction of a Market Fair near the Youth Centre in Mahebourg, he will, for the benefit of the House, obtain from the District Council of Grand Port, information as to where matters stand, indicating the expected completion date thereof.

Deferred from this sitting to: tuesday-09-december-2025

The exchange, in full
Mr Woochit

Madam Speaker, with regard to the proposed construction of the market fair near youth centre in Mahebourg, I wish to inform the House that the original project has not been pursued following the termination of the contractor’s contract in January 2023 and the subsequent arbitration process. After the reassessment in March 2025, it was decided not to proceed with the market fair on that site. Instead, Government intends to develop a multipurpose complex there, but

38 this project has been deferred to the next financial year. As for the market fair itself, it has already been relocated to the Mahebourg market which has been extended to accommodate 206 stalls. Construction works for this extension have been completed and the market fair has been operational since May 2025. Accordingly, there is no completion date for the market fair at the youth centre site as the project is no longer being implemented. Thank you.

Madam Speaker

Yes?

Mr Apollon

Thank you, Madam Speaker. The drugs problem in Mahebourg is affecting the youths of the locality and the construction of this gymnasium will provide more facilities for our youths to practice sports. Will the hon. Minister give this project a priority and get the necessary clearance from the Ministry of Finance for the next year?

Mr Woochit

Sure, Madam Speaker, we will still find a solution for the next financial year. As I said, it has been deferred for the next financial year.

Madam Speaker

Yes, hon. Fourth Member for Port Louis North and Montagne Longue! NATIONAL CERTIFICATE OF EDUCATION EXAMINATIONS 2025 – EXTENDED PROGRAMME – FAILURE RATE