Republic of Mauritius · National Assembly2024–2026 · 26ᵉ THERE MAY BE ERRORS OR INCONSISTENCIES Wednesday, 20 May 2026

The Hansard Record

Parliamentary Questions, in full — public, searchable, copypastable.
Parliamentary Question · No. B/110 · Series B Answered

the swimming pool at Pavillon, he will, for the benefit of the House, obtain from the Mauritius Sports Counc…

Asked by
Ms Anquetil
Second Member · Belle Rose and Quatre Bornes
Addressed to
Youth and Sports
Minister of Youth and Sports
Sitting
Tuesday, 24 March 2026
Question 35 of 81
The question, as placed

(No. B/110) Ms S. Anquetil (Second Member for Belle Rose & Quatre Bornes) asked the Minister of Youth and Sports whether, in regard to the swimming pool at Pavillon, he will, for the benefit of the House, obtain from the Mauritius Sports Council, information as to whether the maintenance and technical works have been completed and, if so, indicate when same will become operational and, if not, where matters stand.


The exchange, in full
Mr Nagalingum

Madam Speaker, I am informed by the Mauritius Sports Council that leakages were detected in the silica sand filter of the Pavillon Swimming Pool and the problem could pose a risk to the filtration system. Consequently, it was decided to temporarily close the facility as from 14 November 2025 to enable necessary repair works. However, during the repair works, additional issues were detected and warranted immediate attention. Consequently, additional equipment had to be procured in order to resolve the main problem. Given the complexity of the repair works, a site meeting was held in February 2026 whereby the matter was discussed between officers of the Mauritius Sports Council and the contractor to determine the best way forward to avoid any further delay in the completion of the works. I am further informed that as at date, the repair works are still ongoing. It would be premature to state a specific date for the reopening of the swimming pool. Madam Speaker, I wish to assure the hon. Member that my Ministry is aligned with her concerns. We are closely monitoring the situation and ensuring the timely completion of the works, taking into consideration that the swimming pool is more than 20 years old.

Madam Speaker

Only questions! Please!

Ms Anquetil

Okay.

Madam Speaker

Only questions! No statements!

Ms Anquetil

Yes, yes, of course! As usual! Je vous remercie, Madame la présidente. Le ministre peut-il expliquer à la Chambre comment une piscine, ayant fait l’objet d’une rénovation récente au début de 2025, a dû fermer de nouveau le 14 novembre pour des travaux supplémentaires ? Peut-il également préciser l’identité du prestataire ayant réalisé cette rénovation et indiquer si c’est le même prestataire qui est actuellement chargé des travaux en cours ? Je vous remercie, Madame la présidente.

Mr Nagalingum

Madam Speaker, this is indeed a very good question that the hon. Member is addressing to me. The bid was awarded to the lowest bidder, namely Espace Commercial Ltée, for a total amount of Rs726,000, including VAT. The works started, like you said, in 2024. We have to deal with the contractor. So, we have a meeting with him this week – I am not sure about the date – and we are going to settle the matter. I know that the swimming pool of Pavillon is very demanding. Both the Minister, Dr. Boolell, and yourself…

Ms Anquetil

And Veda.

Mr Nagalingum

…and Veda Baloomoody as well have already asked me about the date of reopening. We are going to see what we can do.

Madam Speaker

Your utmost best.

Mr Nagalingum

And find a solution.

Madam Speaker

Your utmost best! Yes, your second question.

Ms Anquetil

Je vous remercie, Madame la présidente. Can the Minister inform the House on the monthly fixed costs associated with the closed swimming pool? Thank you.

Mr Nagalingum

I do not have the details with me.

Madam Speaker

Communicate it.

Mr Nagalingum

I can table the answer.

Madam Speaker

One moment! Yes!

Ms Anquetil

A last one. A very short one. Thank you, Madam Speaker. Will the Minister state whether additional public funds will be required to complete the outstanding works? Thank you.

Mr Nagalingum

I think there is a guarantee; the retention money that we have. So, we are going to have the meeting this week, and we are going to find a solution.

Madam Speaker

Okay, yes!

Mr Quirin

Peut-on savoir de l’honorable ministre s’il y a eu des arrangements qui ont été faits afin de permettre aux nageurs et nageuses, qui généralement utilisent cette piscine, de continuer à s’entrainer ?

Madam Speaker

Ailleurs?

Mr Quirin

Ailleurs, bien sûr ! Voilà!

Mr Nagalingum

We have done this, Madam Speaker.

Madam Speaker

Where? In Beau Bassin?

Mr Quirin

Qu’est-ce qui a été fait ?

Madam Speaker

Yes, where?

Mr Quirin

Ils s’entrainent où ?

Mr Nagalingum

Il y a plusieurs places. Par exemple, à Serge Alfred. Il y a plusieurs places où on a relocate the athletes for swimming.

(Interruptions)

Madam Speaker

Ce n’est pas pareil ! Okay, we have finished with Ms Anquetil. Hon. Members, PQ B/111 has been withdrawn. LAND TRANSPORT APPEAL COMMITTEE – APPEALS RECEIVED (JAN 2024- MAR 2026)